on 10-16-2015 8:36 AM
Dear Support team,
I have 5000 Materials having 2-3 alternative bom's, I want to change that 2 or 3 alternative Bom's to default bom for MRP run,
currently I selecting manually everyday 2nd alternative for MRP run .
please provide solution for how to change alternative bom number's......
Hi Swapnil,
You can set "Selection Method" in MRP4 view as 1 - Selection by explosion date. Once done, go to OS32 and make an entry of that material, plant usage , current date along with BOM Alternative you want to use (say Alt 2). Save the changes.
Next time when you run MRP system will pick BOM Alt 2 for that material.
Regards,
Rohit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Swapnil,
As suggested by Caetano you have to maintain the PV in the material master MRP4
if you maintain the 3 PV's with 3 different dates according to dates system will plan your materials
similarly if you have alternative BOM's
while converting planned order to production order system will populate PV list to select the BOM
Regards,
Venkatesh..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
You should create a production version for the material, where alternative 2 is defined. Then, you must change the BOM selection method on the material master, to select it according to the production version.
Regards
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.