Hello

We are trying to create a process order and then we GR'ed the same process order to the restricted stock , but we get the Receipt element with date. we are not sure how and where we need to go and rectify this issue.

I appreciate your help on this issue, Attaching a screen shot of the same.

Error 1.PNG (28690 B)
Former Member
Former Member replied

Hi Akbar


Goto MSC2N in R3 and in classification tab perform consistency check.   Then re-CIF batches again by again generating and activating IM. let me know the result