Resource Management Screen Columns - Changing from Week Number to MM/DD

Hello PPM Experts, I'm hoping one of you can help me resolve an issue I have with the Resource Management screen.

By default the Week #'s are displayed on the screen for the Resources and Staffing screens. E.g.:

But I want to display a traditional calendar unit of measure (i.e. MM/DD).

Have you encountered this challenge and resolved it? I'm running PPM 6.1

If so, I'd love to hear how.

Thanks in advance,

Tom Martin

Tags:
Former Member
Former Member replied

OK folks - here's an update:

I created an OSS message 3 weeks ago and finally got a response.

Apparently this is how it works and it cannot be configured.

Changes to the way the weekly periods are displayed is an enhancement.

I'm closing the message.