Completion date not updated in IP10

former_member1275612
Participant
0 Kudos

Hi Experts,

Work order is generated from maintenance plan. And work order had been TECOd.

Upon completion of work order, completion date is not populated in IP10.

Please suggest.

Br,

Sandeep

Accepted Solutions (0)

Answers (3)

Answers (3)

peter_atkin
Active Contributor
0 Kudos

Sandeep,

Some questions:

  • Does this maintenance plan have multiple maintenance items
  • Has this issue occurred on multiple plans, or just a single plan
  • Are you using any developments in the maintenance plan or work order process? If so, then deactivate these developments and re-test

PeteA

former_member1275612
Participant
0 Kudos

Thanks for your replies.

@Pete - Yes its has 3 maintenance items.

           - It occured only for single plan.

          -  We dont have any devepoments on this.

Morover, i did one thing for it. I completed the Call from IP10 using flag. and entered Completion date frmo the work order.

Now completion date is visible in IP10.

Thanks for your replies .

Br,
Sandeep

jogeswararao_kavala
Active Contributor
0 Kudos

But this does not TECO the Order.

former_member1275612
Participant
0 Kudos

This work order  is already TECOed.

jogeswararao_kavala
Active Contributor
0 Kudos

OK

peter_atkin
Active Contributor
0 Kudos

Sandeep,

If the plan has 3 maintenance items, then was each of the 3 orders TECO'd?

PeteA

former_member1275612
Participant
0 Kudos

Yes Pete,

Other orders TECOd and completion date visible in IP10.

-Sandeep

jogeswararao_kavala
Active Contributor
0 Kudos

Hello Sandeep,

If you have used some program to TECO this work order, which is not a Batch program, then too it can happen. Because in such case the program uses a function module to TECO, which often does not update related activities.

Regards

KJogeswaraRao

MTerence
Active Contributor
0 Kudos

Hi Sandeep,

Can you please share IP10 screenshot ?

Also please refer below note, whether this is related to your issue

1960778 - IP30/IP10 doesn't take completion requirement into account


Regards

Terence