I am looking into if the following is possible in SAP Solution Manager 7.1:
If I create a project (Project A) by setting up the Business Scenario, Business Processes and Process Steps, is it possible to save this information somewhere so that I can use the same information for Project B? (where in Project B the majority of the information would be the same as Project A but some documents may change or be updated). And following that, use the information from Project B for a third project (Project C)?
Is there away to duplicate information for multiple projects and save that information to a central area?
Hi Kelsey,
You can try creating a template project. The template project can be used as a reference for multiple implementations. Usually we make use of the same during global roll outs.
Template Projects - Solution Manager - SCN Wiki
Just go through this wiki link for more info
Regards
Aditya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Kelsey
incase you are doing a global rollout then template project can help as mentioned above
But
if you are not doing a rollout but requirement is a bit different you can still simply
in solar01 of project B choose the source as Project option and then project A which will copy the entire structure as you want
this should resolve and let me know for any further queries
Thanks
Prakhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
10 | |
10 | |
9 | |
7 | |
6 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.