on 10-14-2015 3:17 PM
Hi All
SAP allows to perform several confirmation for one PM Order operation.
For final confirmation it is requaried to set "Final Confirmation" checkbox.
Is it possible to perform several confirmation from SAP Work Manager?
When I confirm operation in SAP Work Manager and transfer data to SAP ERP it allways set "Final Confirmation" to the checked status.
SAP Work Manager 6.2.1.0
SAP Mobile Platform 3.0.7: I
Konstantin,
You can modify this functionality. In OOTB WM application if you go to TimeEntryCreateBAPI class in Java "FIN_CONF" field is hardcoded to true always.
you can create a Boolean property in Agentry client and ask technician to check this property and in Java you can read this from Client and set in Java.
Thanks
Ajitesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
86 | |
10 | |
10 | |
9 | |
7 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.