When i run the PPDS Run (SAP_PP_002) Planned order creating with out Operation data when we see in RRP3
for a product it is creating planned orders with operation data in some period in some period it is creating with Operation data ,Can you please suggest why it is creating with out Operation data
Hi vijaya
Check your PDS or PPM for that material whether the operation are visible or not .IF not check in the ECC whether operation are assigned to material under routing or receipe group.
Regards
virender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vijaya
Have you checked the operation were assigned to your pds . Check for any changes were done under routing group.
Generally SAP_PP_002 Heuristics will not generate receipt or supply to requirement which are already confirmed . SO check any changes are happened in masters of that product . And also check whether your facing these problem for newly created orders or older order also
Regards
Virender