I have the Storage Time Profile Level at Weekly and I want to execute the Supply Plan at Monthly Level. Is this possible?

Regards,

Saabitri

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Saabitri,

Yes,you can execute the Supply Plan at monthly level.

Regards

Avijit

Former Member
0 Kudos

Hi Avijit,

Can you please tell how?

Regards,

Former Member
0 Kudos

Hi Saabitri,

You will only be able to see the data at aggregated level(monthly/yearly). However distribution and production plan will happen at weekly level since some of the  master data are dependent on storage bucket profile.

For example, lead time defined in location product MDT is based on storage time profile. If your lead time is 1 and storage bucket is weekly, then supply and receipt key figure will be visible in different buckets when seen at weekly level but can belong to same month at aggregated level.

Thanks,