on 10-13-2015 6:16 AM
Hi Gurus,
My User created a Service Purchase Requisition (with Acct Assgn Q), lets say for 1.5 Lac, Now PR is released & a RFQ is created & approved, Now a Servcie Order (PO) is created with respect to that Approved RFQ(which is with reference to PR)
What is happening, in CJI5, commitment is coming at both levels i.e 1.5 Lac in PR & in PO.
However ideally commitment from PR needs to be shifted to PO
Please suggest what is missing/needs to be checked out.
Thanks in advance
Hi Sanchit,
please check linkage between all three documents PR, RFQ, PO.
also check line items in each documents. try to run reports for comparing.
if all are correct than follow as per Vijay.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanchit
Please check
1>whether RFQ is created with reference to PR
2>PO created in reference to RFQ
if yes then Check the below notes it would be useful in Resolving your issue
534993 | Short instructions RKANBU01 |
459509 | FAQ: Commitments in purchasing |
1128464 | FAQ: Commitments |
1616873 Purchase requisition commitment not reduced by PO
772206 - Commitment Update in Service Purchase Orders
634298 - FAQ: Commitment update in the service
580595 - Value-based commitment reduction for service PReqs
Regards
Vijay Kumar Hebbal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanchit,
Can you please check S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned .
Thanking you
Vengaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.