Error on Internal Activity Confirmation - Actual Costs not calculated

ashwinipingle
Participant
0 Kudos

Hi All,

I am working on demo system for PS module.

I have a project where I confirm internal activity. Although activity gets confirmed, I also get an error message in the log "Object was not costed".

Also another error message which mentioned that Document not defined for Company code.

After referring to SCN discussions, I found that document type was not defined for Settlement profile. I found the settlement profile and tried to do a tcode OKO7 to set the document type. However I find unable to edit the screen. How can I fix this? Is this PS or FI/CO related issue?

Accepted Solutions (1)

Accepted Solutions (1)

former_member388328
Active Contributor
0 Kudos

Hi Ashwini,

I think you need inform this to your FI consultant, and Check OBA7, whether document type SA is there are not.

Thanking you

Vengaiah

ashwinipingle
Participant
0 Kudos

Thanks for the info. Few settings are not done by FI/CO so I do not have to resolve this further as yet.