Hi Experts,

Please advise if the below scenarios is possible or not:

At Project Defintion level: Plant :1001

Network:1001(Plant)

Internal Activty:1002(Plant)

External Activty: 1003(Plant)

Service Activity:1004(Plant)

Cost Activty: 1005(Plant)

My understanding is ,plant is automtically copied from Project defitnion when we create a Network and the same plant will be copied in to Activities.However,is it possible to create a Project with the baove scenario.Please advise.

Note: All the above Plants belongs to one company code and one controllin area.

Former Member
Not what you were looking for? View more on this topic or Ask a question