Hello All,

When assigning a Sub-process to an organization the validity of

assigned

Sub-process is taking as current date . its very urgent issue and 16th

oct 2015 is my golive ,Please provide me solution for this issue.Below

is my system details

We are in GRC 10.1(GRCFND_A) and SP level is 0008(SAPK-V1108INGRCFNDA)

and please find the attached screen shot for reference.



thanks,

Suresh

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member197694
Active Contributor
0 Kudos

Hello Suresh,

Assuming the issue with time frames

Refer the below SAP KBA

2119204 - Valid From date of Sub Process with respect to the Timeframe selected.

Regards

Baithi

former_member208207
Participant
0 Kudos

Hi Baithi,

This is very confusing to me .

Please see my org structure details

Organization is valid from:    01.01.2013  to 31.12.9999

Central Sub Process is valid from:       01.01.2013 to 31.12.9999

So

I am assigning central sub process to organization..

Issue is  While assigning subprocess to organization ,valid from date taking as system date.

thanks,

Suresh

alessandr0
Active Contributor
0 Kudos

Dear Suresh,

nothing is urgent here on SCN since this is an open community where everyone spends their freetime.

I recommend to check the following SAP note:

http://service.sap.com/sap/support/notes/2076809

Please keep us posted.

Regards,

Alessandro

former_member208207
Participant
0 Kudos

Yes i know Alessandro ,nothing is urgent here on SCN

Thanks for your response,But refered OSS Note related to SP9 and my system GRC 10.1 and SP8

Thanks,

Suresh

alessandr0
Active Contributor
0 Kudos

Hi Suresh,

as far as I see the note can be implemented on SP8. It gets delivered with SP9.

Regards,

Alessandro

former_member208207
Participant
0 Kudos

Hi Alessandro,


I implemented ,but no good luck.

Thanks,

Suresh