Confirmed operation schedule dates changing to the confirmation date

We actively reschedule production orders based on capacity leveling, and supply and demand changes. We also actively measure and root cause on time, and production delays. SAP appears to change schedule dates on confirmed operations from the schedule dates to the confirmation dates when an order is rescheduled. even changing the header dates at times. This obscures original schedules, and prevents accurate measurement . is there a way to prevent this?