We actively reschedule production orders based on capacity leveling, and supply and demand changes. We also actively measure and root cause on time, and production delays. SAP appears to change schedule dates on confirmed operations from the schedule dates to the confirmation dates when an order is rescheduled. even changing the header dates at times. This obscures original schedules, and prevents accurate measurement . is there a way to prevent this?
Hello, it is only possible to prevent this behavior for partial confirmations, by changing the "shif order" indicator on OPU3. For final confirmations this is standard and cannot be avoided,
BR
Caetano