Hi,
I am trying to create a service activity and I do this by dragging from the templates into my project structure. However the Service Activity detail screen prompts me to enter Info Record and further provides me with Service Entry screen. Further it creates a PR on save (that is because I have set it to Immediate on save).
I know the cycle of Service activity as PR-->PO-->SES-->Accept services-->Invoice-->Payment
I am assuming that this service activity will be costed from Service Entry details and not Info record.
Should I create a PR&PO first and then use it in the service activity? Can someone point me to the process of using a service activity and from where the costs will be picked up from?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ashwini,
When you are pulling the Service Activity and attaching to network, a pop-up will appear to enter the service package or limits.
Once you assign the service, the tick will be set automatically
You need to fill certain details like Pur. Org, Purchase group, material group and press enter, a pop-up will appear to maintain limits
Regards
Terence