In Project Builder (CJ20N) can someone explain the differences between Save (Ctrl + F2) and Intermediate Save (Ctrl + Shift + F10) ? I know that with Intermediate Save the user does not have to exit the project that he/she is working on.
Thanks in advance.
Hi Pratap,
You have already given the answer , so what kind of information you are looking for.
In certain companies, single project will have hundreds of WBS elements and thousands of activities, so each time you need to save, exit and again come back to the transaction and search for the activity. To avoid this delay time, SAP has provided this Immediate Save, so users need to go out of the transaction, but they can continue doing it.
This concept is very efficient and quick.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.