Hi team,

We are not able to replicate po's and confirmations form SRM to ECC.

This issue is pertaining from yesterday

All the connections are fine ,Can somebody help us.

We are in SRM 7.0

Po's are getting created in SRM and not getting replicated in ECC system we are using extended classic scenario.

The same with confirmations,Confirmations are getting created in SRM and IDOCs are not generated which transfers data from srm to ECC.

Thanks,

Sai

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Sai,

- Did you verify if the RFC connection is getting established b/w your SRM & ECC systems ? (This is to check PO transfer issue)

- Check if BBP_GET_STATUS and CLEAN_REQREQ jobs are running in SRM & ECC systems

- Check for logs in SLG1 and in the application monitor in SRM portal

- Look for dumps in ST22

If everything looks fine, run the FM BBP_PD_PO_TRNASFER_EXEC by giving the PO GUID and debug to check why the PO isn't getting transferred to ECC system.