on 09-29-2015 2:20 PM
Hi,
I'm using a BW extractor (2LIS_13_VDITM) to pull the data from ECC and load to EDW(oracle).
I would like to know if there is a way in BODS to have these jobs scheduled dependent on the SAP jobs. In this scenario i would like to extract the data from the extractor only when the job in SAP completes loading data to extractor.
Anybody tried this before? Your replies would help.
Thanks,
Rohith
If I am correct informed, you could trigger DS jobs from BW process chains. So you should be able to attache the DS job behind your SAP job.
Another way could be the BOE Platform, if you license this. On the platform you could use additional events.
Personal I would try / prefer the first way.
Hope I could help,
Severin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
10 | |
10 | |
9 | |
9 | |
7 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.