on 09-29-2015 7:45 AM
Hi everyone,
Our APO team has generated a datasource and it is replicated to self BW system.
Now when i transported RSDS version of data source it got failed saying - Infosource is not available.
Then i collected data source OSOA version in RSA6 and trnasported which got activated n QA.
But when i try to load data to PSA we found that Datasource is not assigned to planning area in QA.
Please help me on this.
Hi Chaitanya
Important thing with Datasource in APO, specially darasource which are created based on Planning Area - Transport should include Datasources from DataSource (Active Version) and DataSource in BW.
You can use transaction /SAPAPO/SDP_EXTR to replicate the datasource before creating the transport.
Please check.
Thank you
Satish Waghmare
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chaitanya,
Please check the data source for the planning area in /SAPAPO/SDP_EXTR - here you will have option to check, repair and replicate the data source for the planning area if it is present in QA.
Regards,
Alok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.