Dears,
My Case is as follows:
a material component is assigned to the activity in PS and the material takes 1 month for example to be delivered and it's entered in the lead time for the material in MM .
I need to know if it's possible for this lead time to appear in the project builder or if I can use material motoring dates in PS for this and how it can be set
Attaching a compnent in PS sets the requirements date and sends that to MRP. MRP does the backward scheduling calculations and determines when the PO needs to be placed or the production order needs to start.
You can use the MRP transactions to monitor it or you can look into PROMAN (PS Procurement Manager) to geet a project oriented view into MRP.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.