on 09-28-2015 7:40 AM
Hello Experts,
Before Go-Live, we are going to create/upload templates for running project .
Kindly suggest as to how we upload the costs on these existing projects for reporting purpose exclusively, and forthcoming costs will be booked in regular way.
Kindly suggest .
Best Regards.
Hi,
My suggestion take two g/l accounts in same grouping in P&L . On debit side use WBS and on credit side use a dummy cost centre. Post it with cut over date or before cutover date.
This is only a workaround. If you have any planning or cash flow analysis It might affect that also, please take care of that in consideration.
Thanking you
Vengaiah