We have implemented fund management, while creating new Wbs element using Tcode CJ20n (project builder), we faced an issue we are unable to save the project. The following error are there after seeing the in logs and cost calculation.
i have come across similar issue in this forum, but unable to find exact solution.
Thanks in advance.
Message no. CO634
thanks
karam
Hi,
If you integrated PS with FM, then commitment item should be introduced at the master data level. So, you have to preview a rule in FMDERIVE, which would derive it for WBS, or introduce it manually.
Regards,
Eli
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Eli,
As i am unable to find any commitment and fund center fields in the tcode CJ20n while creating the new wbs element. As this has to be derived from fmderive or can we directly assign.
Is there any config to be done to the project as this project is also having the networks.
Thanks and regards
karam
Hi Karam,
In that case create the rule before creating the WBS Element. By itself creation of the WBS Element will not create this error as there are no values posted. This can happen, however, if you are using Network Orders.
If you are then you should check IMG -> Public Sector Management -> Funds Management Government -> Actual and Commitment Update/Integration -> Integration -> Maintain Field Status for Assigning FM Account Assignments to see if you have maintained the appropriate field status for the Network Order. This way you can enter the values while creating the master data of the network.
Thanks
Shyam
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.