Dear Experts,

With reference to the capacity planning function for PM orders, we can assign splits(personnel numbers) to an operation.

Dispatching is carried out via CM25 and other planning boards, however when we select the dispatch indicator manually to the split (requirement assignment tab)no status is set in the status tables?

Which table can we see this indicator set?

Accepted Solutions (0)

Answers (1)

Answers (1)

peter_atkin
Active Contributor
0 Kudos

Gaurav B


The DSPT status is set against the operation.


See table JEST using the operation object number (AFVC-OBJNR e.g. OV100041281600000001).


PeteA

gaurav_b2
Explorer
0 Kudos

thanks Pete,

I did check that however,the  status is not set in JEST for operations where the tick box is set manually.(I'm referring to the dispatch check box if set manually by the user in the order requirement assignment tab)

If we use CM25 then the tick box is set in the order and a corresponding system status DSPT is set in the table.