on 09-21-2015 3:03 AM
Hi All,
Have a question component issues to production order-Suppose we release production order. tsk will be created, and then we want to change one of the component , how we can do it?. Before release of production order components can be changed. After release, is there any alternate way that we can refer the components to the production order
Thanks
Vijay M
Hello Vijay,
Mr. Anant is right that you cannot add products to an order once it is released as that is the expected system behavior but you can manually add input products in input product tab. You can also add resources/services under activities if required additionally.
Regards
Leo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi leo,
Thanks for this process, i have never use this before.
I have just use NEW REPLENISHMENT & REMOVAL.
Thanks & Regards,
Anant Patel
SAP BYD FUNCTIONAL CONSULTANT
Phone: +91-9716100326
Email: anant3113@gmail.com
Skype: anant.3105
Hi Vijay,
You can change any of the component until production order is released.
After realease of production order there is no way to change the component beacuse the supply & make tasks are created.
Thanks & Regards,
Anant Patel
SAP BYD FUNCTIONAL CONSULTANT
Phone: +91-9716100326
Email: anant3113@gmail.com
Skype: anant.3105
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.