Production Order Issue

Hi All,

Have a question component issues to production order-Suppose we release production order. tsk will be created, and then we want to change one of the component , how we can do it?. Before release of production order components can be changed. After release, is there any alternate way that we can refer the components to  the production order

Thanks

Vijay M

Former Member
Former Member replied

Hello Vijay,

Mr. Anant is right that you cannot add products to an order once it is released as that is the expected system behavior but you can manually add input products in input product tab. You can also add resources/services under activities if required additionally.

Regards

Leo