Hello,

I've read it is not possible to schedule multiple work modes for systems (workcenter "technical administration" > "work mode management" in solution manager 7.1 SP12). So here's my question: what is the best practice in following example:

In our company:

Work mode "peak business hours" scheduled for all systems,weekly from Monday - Friday from 08:00 to 17:00

Work mode "non peak business hours" scheduled for all systems, weekly from Monday - Friday from 17:00 to 08:00 and Saturday and Sunday from 00:00 to 23:59

Now, if there is a "planned downtime" on Friday from 15:00 to Saturday 08:00 for all systems, what is the best way of planning this work mode "planned downtime" the simplest, fastest, easiest way?

a BIG thanks for any help!

Best regards,

Kenny

Former Member
Former Member replied

Hello,

Everything is OK now. We were managing our work modes in own language (dutch). When logged on in English, everything seems to work the way it should work.

Thanks for all your replies.

Best regards,

Kenny