calculate the task estimated time in DMB order

Hi Experts,

I have a requriement for calculate the task estimated time,

The detail like this: when i assign a item to a task no ,i want the time of this item spended can add on the estimated time,and  i assign the another item to this same task no, the time can sum and diaplay on fied "estimated time",

2.jpg (98038 B)
1.jpg (144252 B)
Former Member