Planned orders not being scheduled

Planned orders in my plant are not being scheduled properly.  I checked for a valid routing for the material and that exists.  When I go into the planned order, the detailed scheduling and rough cut tabs are not visible.  I can go into the planned order, hit "Shift F6" to manually schedule the planned order and at that point the tabs appear.  Why will it not do this automatically?  I have 1200 planned orders in my MRP queue that I want to do this to so I can see overall capacity requirements for the work centers used in those routings/materials but do not want to go through 1200 manually and do this.  Can anyone help?