We are implementing the SAP in Textile Industries, based on discussion i have one question about subcontracting using split valuation.
Client having Semi finished material which they do in-house production, Procurement and Subcontracting. so in material master MRP2 its mentioned procurement type X (Both procurement types) and splitt valuation activated.
In Valuation variant strategy define for All tabs.. like Material/ACtivity/Subcontracting/Ext proc/Misc/OHead etc. for subcontracting strategy define as Net PO price, Gross PO Price and Effective price from purchase order.
when we are doing the costing using CK11n we are unable to getting the subcontracting prices for same product which subcontracting from outside.
Thanks in Advance.
Thanks
Akesh Agrawal
Hi Akesh
1. You will need to maintain Spl Proc Key as 30, together with X.. 30 indicates Sub Contracting
2. Ideally. in this case, you should go for Mixed Costing
3. Define a Qty Structure Type in IMG and assign it to Costing Version 1
4. Create Proc Alternatives in CK91N
a) Proc Alt 1 using PRODUCTION as the Process Catg
b) Proc Alt 2 using SUBCON as the Process Catg
5. you can also select the respective Valuation type for each Proc Alt, incase you are using Split Val
6. Now Maintain Mix Ratio in CK94, depending on what portion of the time you make it in house and cub-contract it
7. Now do CK11N
System will calculate individual Std cost for each option as well as the Wegihted Avg cost
Br, Ajay M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.