How to add a new WBS Element to Existing Project using BAPI_PROJECT_MAINTAIN?

0 Kudos

Hi Friends,

     I have created a Project 'ABC' with WBS elements as like below

      ABC

        |____1

        |         |_1.1

        |         |_1.2

        |         |_1.3

         |____2

                  |_2.1

       Now i wanted to add a new WBS element(1.1.1) Under (1.1) using BAPI_PROJECT_MAINTAIN.


      So please give your suggestions to achieve this requirement.

Thanks,

Dinesh

Accepted Solutions (0)

Answers (1)

Answers (1)

sunil_yadav2
Active Contributor
0 Kudos

Hi Dinesh,

BAPI Will work as hierarchy maintenance so you need to maintain like WBS_LEFT and WBS_UP.

then you will be able to create levels of  WBS within project.

thanks

Sunil

0 Kudos

Hi Sunil,

   Thanks for your reply.I have tried with WBS_LEFT and WBS_UP,but i couldn't achieve.If you don't mind can you please let me know how to fill the entries for creating the WBS element (1.1.1) under (1.1) and (1.4) under 1.

PROJECTWBS ELEMENTWBS ELEMENT DESCSHORT IDWBS_UPWBS_DOWNWBS_LEFTWBS_RIGHTACCOUNT ASSIGNMENT ELEMENT
ABC1.1.1Test1.1.11.1X
ABC1.4TEST 1.41.411.3