Hi experts,

I got a strange behaivour of GATP Availability Check, I'm using a combination of basic methods and then CTP as follows:

  1. Product Availability Check
  2. Product Allocation
  3. CTP (After executing all basic methods)

The problem is that the availability check results are blank after performing the product availability check:

I have made some simulations of every basic method individually, for the product availability check the result is No Availability and that is correct because the ATP Quantity is negative.

For the Product allocation there are available allocations quantities for the next three months.


If I'm right the system should create a planned order assigned to the PO for the total quantity.


Here are some pictures of Check Instructions and Scope of Check.

Thanks in advance for your help and advice.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Mario,

I think that the problem is that as long as there is no allocation quantity available, no quantities can be confirmed. Allocation is used to limit the quantity that is confirmed.

Add some allocation quantity and try again.

0 Kudos

I've added allocation quantities but it still doesn't work. I also tried eliminating the second step (allocation) without success.

Answers (0)