Change Document number is not getting generated

Former Member
0 Kudos

Hi Experts

We have custom transactions for request for change and change documents . We are able to create change request and insert a scope

Change Document is getting approved with the status but the document no is not getting generated after status changed

-Saravana

Accepted Solutions (0)

Answers (1)

Answers (1)

rishav54
Active Contributor
0 Kudos

Hi Saravan,

Please check the copy controls for this.

Solution Manager 7.1 CHARM Configuration Part 3 - YouTube

2. Check the ON_CREATE PPF actions responsible for this.

When you change the status of change reqeust to "Being implemented'. the corresponding action _ON_CREATE for normal change should be execute.

Most commonly the error was either "HF_STATUS_*" was not assigned with appropriate values (e.g E0001). So check that and it will solve your issue.

Change Request Management (ChaRM) - How to enhance the standard workflow - SAP IT Service Management...

Please keep us posted

Thanks

Rishav

Former Member
0 Kudos

Hi Rishav

Thanks for your update

In our case change document is getting generated but the change document number is not getting generated

document status is approved

-Saravana 

rishav54
Active Contributor
0 Kudos

Hi Saravana,

Yes you need to move the RFC into Being implemented phase, then it will generate.

Number ranges you an check if it is assigned in tcode SNRO, check fro CRM_SERVIC, also check in the transactions or charm setup whether this number range is assigned to your normal changes.

I hope it should resolve your issue.

Thanks

Rishav