Pl tell how the "mode priority" in PDS will come from ECC to Use REM Huristics
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Vijaya,
I would say that expert Rupesh's screenshot shows everything required in order to display the detail within a PDS record in transaction PDS_MAINT. It is unclear to me where your difficulty lies.
Show us what steps you have tried so far; with screenshots.
Best Regards,
DB49
can you please reply and suguest how to achive the mode priroty and also to use REM huristics
reqirement is to use the primary resource first then use the alternative resouce after loading full of primary
resource ,i am thinking we can achive with REM huristics but when i am checking it is deleting the planned order,please suguest
Hello,
Check your master recipe or routing first, there should be valid operation which should be relevant for scheduling. Then CIF the PDS once again CFM1/CFM2, RIMODINI or CURTO_CREATE.
Operation data should be there in PDS. If you have the operation data then in PDS_MAINT maintain the mode priority and then run CURTO_CREATE again.
Best Regards,
R.Brahmankar
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.