In Service entry different WBS used than PO hence commitment value still open

Hi Experts,

I have a scenario where user has changed WBS while posting Service entry sheet. For example I have created PO for Value 10,000 with WBS XXX

but while posting Service entry user changed the WBS to XXY. Now actual has been posted to WBS XXY but now commitment for 10000 is blocked with WBS XXX. How can we rectify this case? Please help us to resolve this issue.

Thanks & regards,