Hi,

When I create PR item without mateial(entering only text),how the system will calculate release date(tab:Quantities/Date)?Any tips please? Thank you.

I know that  when I create PR with mateial,release date will be  be calucalted based on planned delivery date.

Regards,

Accepted Solutions (1)

Accepted Solutions (1)

former_member183424
Active Contributor
0 Kudos

System will take the PR creation date as release date when you create a requisition without material master.

jaheer_hussain
Active Contributor
0 Kudos

what is the meaning of release date?

For example my release date 15.09.2015.

former_member183424
Active Contributor
0 Kudos

Please read the KBA document 1909157 - Purchase Requisition Release Date is not updated ,it explains what is release date. Also press F1 to get more details.

Do you have any processing time for plant in img OLME-Purchase Requisition-Processing Time ?

jaheer_hussain
Active Contributor
0 Kudos

yes we have one day as processing time  in IMG for this my plant.

former_member183424
Active Contributor
0 Kudos

I've just checked the same in my system. System is picking all dates as current date.

Can you please share screen shot of PR.

Also check is there any badi or exit implemented for requisition.

jaheer_hussain
Active Contributor
0 Kudos

Here you find below PR screen.

former_member183424
Active Contributor
0 Kudos

Your delivery date is showing 09.05.2016. Why ?

As per you delivery date and processing time, system is calculating the release date.

You need to focus on the delivery date. Why it is showing a date which falls under next year.

jaheer_hussain
Active Contributor
0 Kudos

I do undestand that release date means the PR should be converted into PO before that date.Am I right?

former_member183424
Active Contributor
0 Kudos

Yes. It does mean PR should be released on/before that date. So that material will be available on the date when it is needed.

jaheer_hussain
Active Contributor
0 Kudos

OK.

If User does not make approve(release strategy) before or  on release date,then how material will be available on required date??

former_member183424
Active Contributor
0 Kudos

If you do not release the requisition, then you can't process further (like create PO with regards to this requisition). So material will be not available on required date.

By the way, this is just a calculation date from system. You can proceed further as per your business scenario.

The standard effect of this field is explained.

Answers (2)

Answers (2)

BijayKumarBarik
Active Contributor
0 Kudos

Hi,

As you said for material- the release date  calculated based on planned delivery date but in case of service or with consumption PO with entering text- system auto calculate the release date  by keeping planned delivery date as ZERO value.

You can try with following options to know how system calculate  release date:

Option-1:=>

Delivery Date : 30.09.2015

Request date  : 02.09.2015

Release Date  : 30.09.2015

Pl. Deliv. Time: 0

Option-2:=>

Delivery Date : 30.09.2015

Request date  : 02.09.2015

Release Date  : 29.09.2015

Pl. Deliv. Time: 1

Option-3:=>

Delivery Date : 30.09.2015

Request date  : 02.09.2015

Release Date  : 23.09.2015

Pl. Deliv. Time: 7

Regards,

Biju K

jaheer_hussain
Active Contributor
0 Kudos

Hi,

what is the exact meaning of this statement,please?

Purchase Requisition Release Date

Specifies the date on which the purchase
order
should be initiated on the basis of the purchase
requisition
.

former_member189776
Participant
0 Kudos

Hi Jaheer,

The release date is based on:

o   The purchasing department processing time defined for the plant

o   The planned delivery time from the material master record or purchasing info record

o   The delivery date

o   The goods receipt processing time from the material master record

In your case release date will be same as the delivery date.

Thanks.