Error GMMASTERDATA225

Former Member
0 Kudos

Hi,

We are getting "Budget validity time slice 020 cannot be changed after budget is assigned" error when trying to extend budget validity dates in a grant. We are upgrading to ECC EhP7 with SAP_APPL at SAPKH61708 and EA-PS at SAPK-61708INEAPS.

This error doesnt pop up in our current EhP4 systems. How can I mitigate and change the budget validity dates without an error?

Thanks for your help.

Regards,

Nathan

1 ACCEPTED SOLUTION

Former Member
0 Kudos

Ok so here are the alternatives.

1) Create a timeslice with new BVP and transfer the budget values to the new time slice. Ofcourse this is a workaround and I didnt prefer that to begin with.

Secondly,

2) SAP came out with a pilot note - 2209635(which they have released to everybody now) rectifying the anomaly.

Hope this helps to those who run into the same issue.

Regards,

Gughanathan

View solution in original post

1 REPLY 1

Former Member
0 Kudos

Ok so here are the alternatives.

1) Create a timeslice with new BVP and transfer the budget values to the new time slice. Ofcourse this is a workaround and I didnt prefer that to begin with.

Secondly,

2) SAP came out with a pilot note - 2209635(which they have released to everybody now) rectifying the anomaly.

Hope this helps to those who run into the same issue.

Regards,

Gughanathan