Hi,

How do we maintain details of predecessor & successor run in IBP ?

In case, I want below 3 algorithms to be executed on this sequence.(Immediately one after other)

  1. Forecasting
  2. Inventory optimization algorithm
  3. Heuristics in Supply Planning

In case of APO we can use process chains / External background scheduling tool.

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

parveen_kumar6
Advisor
Advisor

Hello

You can try the group operator. The group ( GROUP ) operator allows you to define a group of planning operators that are executed in a single batch job in a defined sequence. Since a group operator can be run in batch mode only, all planning operators that you assign to a group operator must also be configured to run in batch mode.


You may refer to the model configuration guide for more details.