CJ91/CJ92 Standard WBS Transport

Former Member
0 Kudos

Hi All,

in my development Systems i have created a some of Standard WBS (submission) TA = CJ91/CJ92. Now we would like to transport this Standard WBS to the Q-System.  Do any body have a experience or a advice

Thank you so much for any Idea
KR
oal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Omar,

No you cannot Transport the master data such as Project structures (Standard) from one System to another.

You Need to recreate it

http://help.sap.com/erp2005_ehp_03/helpdata/EN/0b/2a6266507d11d18ee90000e8366fc2/content.htm

Regards

Vittal

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Its better to recreate the same WBS in another client. Please go through the following thread.

http://scn.sap.com/thread/3632108

Regards,

Amit

Former Member
0 Kudos

Hi All and thanks a lot

this issue is solved now.

we have to crate in each systeme the Standard WBS

KR

Former Member
0 Kudos

Ideally

You Need to create Standard elements in Q system

Development D System is used only for customizations. So that These customizations are trasnported to Q System as and when required and you can test your master data and process flow in Q system

Hope this helps

Regards