Not getting Planned Revenue

Former Member
0 Kudos

Hi All,

Milestones in our projects are linked to billing plan in Sales Order and WBS is also tagged in the acct. assignment at the item level but I am not getting the planned revenues in any of the PS reports. Please suggest?

Thanks,

Ellie Mill

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In continuation of what I had suggested above. Please cross check following settings also.

1. Go to OPSB. Make sure following option is ticked.

2. Go to SPRO->Project System->Revenue and Earnings->Planned Revenues->Automatic Plan Revenue Calculation->Specify revenue plan update from sales document. Here, you need to make sure following option is ticked.

Regards,

Amit

Former Member
0 Kudos

Thanks Amit and Vittal,

Closing the thread.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello,

I just encountered this issue while refreshing the process.

It was due to the missing element in the planning Profile in PS

Sounds small but we think more complex for smaller issues

Hope this helps

Regards

Vittal

Former Member
0 Kudos

Hi,

Just go through the following threads. This might help you.

Actual Revenue Not Updating in PS Reports | SCN

Regards,

Amit