on 09-01-2015 6:11 AM
Hi All,
Milestones in our projects are linked to billing plan in Sales Order and WBS is also tagged in the acct. assignment at the item level but I am not getting the planned revenues in any of the PS reports. Please suggest?
Thanks,
Ellie Mill
Hi,
In continuation of what I had suggested above. Please cross check following settings also.
1. Go to OPSB. Make sure following option is ticked.
2. Go to SPRO->Project System->Revenue and Earnings->Planned Revenues->Automatic Plan Revenue Calculation->Specify revenue plan update from sales document. Here, you need to make sure following option is ticked.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
I just encountered this issue while refreshing the process.
It was due to the missing element in the planning Profile in PS
Sounds small but we think more complex for smaller issues
Hope this helps
Regards
Vittal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Just go through the following threads. This might help you.
Actual Revenue Not Updating in PS Reports | SCN
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.