on 08-27-2015 7:48 PM
Hi everyone!
I'm having trouble with solman system preparation procedure at step 5.
The transaction NGTRACE shows the following error:
“Class CL_E2E_DPC_SP_MIGRATION returned "Successful? FALSE!" “MAI Data Migration ended with "Error? TRUE!"
In transaction SLG1 for the parameters "Object" = E2E_ALERTING and "Subobject" = DPC_SETUP, the error message 'DPC Migration SP9 completed with failure.' is displayed
I have already applied the sap note 2061752 but still do not working.
My envirorment: Solution manager 7.1 with SP13!
I'll be very grateful for any help you can provide,
Solution SAP note 2155813
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
13 | |
13 | |
11 | |
11 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.