on 08-27-2015 5:48 PM
Hi All,
currently we are using PI 7.1. with SAP EHP 1 SPS 09. we would like to install a DAE, so can we use AEX as DAE, if we install AEX can this AEX can use the current PI 7.1. ID. IR objects.
Our objects are ready in current PI but we would like to have a DAE and we need to switch the current PI channel to AEX in ID by just changing the Adapter engine from CAE to DAE ? or do we need to redevelop the objects in AEX ?
Please advice,
Thanks -
Lakshman
Laxman,
AEX is from NW 7.3 version only.
If your PI and AEX are on same version, you can use the same ESR for both and during the configuration select where the ICO will run.
You can reuse the existing PI objects(AEX compatible) objects and no need of redevelopments.
Also for a centralized monitoring you will have to use the Solution Manager.
I believe you will have to upgrade your current PI to the same version as that of AEX.
regards,
Arun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
AFAIK - For AEX (Integrated Configurations), both sender and receiver channels should run on the same engine.
So i don't think it's possible for you to have AEX as a decentral AE to host/run one of your channels on it.
What you can do is.
Install AEX and enable the communication b/w two Pi systems using soap adapter.
All the development and mappings will be on your PI system and a pass through scenario on AEX.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Scenario is from external -> pi - > ecc, so we are planning DAE as AEX for soap sender from three to internal pi IE, from IE messages has to send to ECC, and it is synchronous flow. As this is external communication we can not give access our current pi so we need to have DAE,
We can install AEX as DAE but i am looking does the DAE AEX can use correct PI ID and IR or not and is the AEX can support for PI 7.1?
It does not seem possible, see this System Landscape Recommendations for SAP NetWeaver Process Orchestration 7.3 EhP1.3 if you "7.1" was a "7.31" could use "Central ESR"
>>>We can install AEX as DAE but i am looking does the DAE AEX can use correct PI ID and IR or not and is the AEX can support for PI 7.1?
I agree with Stefan on the usage of IR and ID.
Having said that, you don't need to have any design object even it is on the sender side.
Just define a pass through scenario on AEX and hold all your mappings in your PI system.