on 08-24-2015 4:53 PM
Hi
Please suggest what this Heuristics(SAP005-Schedule Operations,/SAPAPO/HEUR_DISPATCH) does for deallocated planned orders:
We are getting Deallocated Planned orders when we run the Rescheduling job,Requirement is not to get deallocated planned orders
when i see in google there is one Huristics "SAP005-Schedule Operations,/SAPAPO/HEUR_DISPATCH" for the below link
http://help.sap.com/saphelp_scm700_ehp03/helpdata/en/e7/4dc95360267614e10000000a174cb4/content.htm
Please suguest to use the delocated planned orders
Hello,
During rescheduling of operations, the planning horizon period is always taken from the time profile.
Please check all your operations comes under time profile
Also check strategy settings of the current strategy profile and the Log of planning run is there free available capacity to schedule these operations.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.