on 08-24-2015 9:42 AM
Hi Experts,
My DP Planning bucket is Monthly and my SNP Planning bucket is weekly. Now when releasing forecast from DP to SNP what setting is required so that the forecast should correctly sit in the weekly buckets in SNP and also vice versa.
Thanks
Ramesh
Ramesh,
First you need to create a storage bucket profile (/sapapo/tr30) with number of buckets and periodicity as weekly.
Then you have two options:
Try with above and let us know if it resolved your issue.
Not sure what do you mean by "vice verse"? Are you copying back the results of SNP to DP?
Regards
Rahul