Error When Running Unconstrained Planning

wnman2005
Explorer
0 Kudos

We are getting this error when running the Unconstrained Planning Simulation.  Please advise on how to resolve this.  Thanks for your help!

I've also attached the full error log.

Invalid production resource data for source ID 201_1204, location 201 and resource 201 RES1: resource location product master data is also specified

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi William,

Check if you have same resourceID in resource location product master data as well as in production resource master data. Same resource cannot be used for production and handling. Maintain it in only one master data and then try unconstrained run again.


Best regards,

Rohit

wnman2005
Explorer
0 Kudos

Thank you all.  It was fixed!

Answers (1)

Answers (1)

anil_gupta8
Active Participant
0 Kudos

Hi Ni

This error means that your source id define in production  source is different than defined in production resource.....

Please create production  resource and instead of entering  source id  select the one  you defined in the production source. This will come as  available value..

As  I understand  system doesnot check /validate the source id during production resource.. Sometime a typo  can cause this issue

Please review if this fixes your issue

Regards

Anil