    system analysis step lower node has been completed, but the display in process:running.What causes it

    as follows,It has more four hours

   and the detailed steps

 

What causes it? Please give help!

Accepted Solutions (0)

Answers (1)

Answers (1)

rajesh_kumar2
Active Participant
0 Kudos

What is the SP release of DMIS_CNT you are using in your system ?

Mostly this should be an optional activity and it need not be executed to

complete the system analysis phase.

In case you want to move ahead, you can simply mark this as manually completed using the troubleshooter "Setting status of an activity manually".

Thanks,
Rajesh

Former Member
0 Kudos

Hi Rajesh

     the newest SP release DMIS_CNT 2011_1_731 SP09.

Do as you say, but to no avail.now i can't proceed with the next activity.

Former Member
0 Kudos

hi  Rajesh

     it is not an optional activity.please help me!

rajesh_kumar2
Active Participant
0 Kudos


You have mentioned that your systems are on SP09, but from the screenshots attached by you, it seems to be something different.

It could be that the DMIS / DMIS_CNT installation was not correct.

As I mentioned this activity should not have been in your TDMS tree.

I would suggest you to open a message with SAP to analyze this situation.

Thanks,

Rajesh