Hi ,
If I have 3 different process in single business scenario , can I correlate them with two different condition based on two different attribute? It means, suppose my first process starts running from 1st process followed by 2nd process and ending on 3rd process,and In second time starts running from 2nd process and ending on 3rd process , can I correlate them in single business scenario with two different correlation condition with different attribute?
Thanks,
Sumit
Hello Sumit,
Yes, you can have multiple correlation condition but the conditions should be defined such that there are no 2 or more conflicting paths to reach to end. For Example, Lets say you have these 3 correlation conditions for each of your processes P1.a P2.b and P3.c , so you have have these sets of correlation condition :
Option1 :
Correlation Condition : P1.a, P2.b, P3.c
Option 2:
Correlation Condition 1: P1.a, P2.b
Correlation Condition 2: P1.b, P3.c
Correlation Condition 3: P1.a, P3.c
What you cant have is : P1.a, P3.c and P2.b, P3.c as they conflict each other.
Hope that answers.
Regards,
Archana
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Archana ,
Thanks for your response ,
Actually i have requirement like this
ERP SRM
1)PR1 RFX(PR1+PR2+PR3)
1.a)Item1
1.b)Item 2
.................. Item1
Item2
2)PR2 Item3
2.a)Item1 Item4
2.a)Item2 Item5
2.c)Item3 Item6
Item7
.................. .......
3)PR3
3.a)Item1
3.b)Item2
.........
The relation between PR item and RFX item exist in back-end tables but the item number in pr and RFX will not the same
That time how we correlate ?
Thanks,
Sumit