Dear All,

Currently, i am using PS to control and monitor my project. Project officer has to create PR in CJ20N if i need to buy a new materials, but if 1 user is using CJ20N, so, purchaser cannot generate PO reference PR cause of 1 WBS has only 1 PR. My question is, how can i create multiple PR within 1 WBS in CJ20N??

Regards,

Rtn

Accepted Solutions (1)

Accepted Solutions (1)

former_member341917
Active Participant
0 Kudos

Hi,

Remove the Collective PR Indicator in OPUV Transaction(Network Type Parameters). you can have multiple PRs in 1 WBS Elements.

Regards,

Kusam Avinash

ratana_pouy
Participant
0 Kudos

Thanks Kusam Avinash!