Dear Gurus,
I have some cost which I posted to WBS using FB02 but at the same time I also do have cost which includes labour work and their time charges on WBS. I want to know do I have to use secondary cost element to settle the time charges or should I go with Primary cost element only.
Regards,
M.Reddy
Hi,
This is too basic. Please go through the forum before posting. You could use your secondary cost element. Define the settlement rule using OKO7 and maintain the secondary cost element as in source.
Regards,
Amit