Our company is on the SAP BusinessObjects BI Platform 4.1 Support Pack 4.

Our team has built 100 Webi reports, and need to create 10 different schedules per report. (roughly 1,000 report schedules total)

It's a very tedious process to create 1,000 report schedules.

I was wondering if these report schedules will promote from one environment to the next, without the need to manually recreate all 1,000 report schedules.  Is this possible?  Any insight you can provide is greatly appreciated!

Tags:
replied

Hi,

Under the promotion management, select ->Settings -> Job Settings -> Select check box "show completed instances in the dependencies page".

After that at the the time of promotion in the manage dependencies you can select the scheduled jobs for migrate in other environment.


Amit