on 08-12-2015 11:46 AM
Hi Friends,
I have maintained classification for a phase in recipe and it has around 5 resources assigned to it.
I believe we can have only one operation timing for the phase.(like setup time, process time etc) for the same phase whatever be the resource assigned out of the 5 from classification.
Is it possible to assign different timings if we work with different resources out of the 5 means how can we put different timings based on the resource selection?
Thanks in Advance.
Thanks,
Prasanth
Hi Prasanth,
If I understand your question right, there is an option of entering the times on each resource, so I guess you can enter the times (setup / produce / teardown) in the resource master and that once you adopt a particular resource, its values will be involved. please check and let me know if this is your requirement, if not please be more clear so that I can assist you further
Thanks
Gomathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.