Only HUs with storage process can be completed.......

Hi,

IN POSC outbound process.

I am following 3steps

Step1: OB01 - Picking

Step2: OB02 - Packing

Step3: OB03 - Staging Area (Put away)

While creation of the warehouse task it is picking from the source bin OB01 task is creating properly, once it is confirm OB01 task at the same time system has to create OB02 task is in open status and OB03 task will be in waiting status.

in my case it is not happening, but the material is available at work center (/SCWM/PACK)

i  create new hu in work center, but hu is not getting storage process as well as external step in details1 tab.

so, i am unable to close the hu.

My product is without hu and i have defined storage process with auto w.task

So, please suggest me if there is any setup has to be done..........

and also please correct me if i am wrong....

Thank you