Dear all,
I am looking for some insights into your experiance with Consignment driven
Processes in SRM / R/3.
E.g. there are no technical issues using consignment items in GOAs and distribute
the GOA into R/3. But from pricing perspective, the price needs to be zero as
well the committment needs to be only build in the moment when the good is used.
Does anybody have experiance with using consignment in a SRM / R/3
environment and insights into the issues and the solution?
Many thanks,
Claudia
Does anybody have experiance on using Consignment Items in Contract
Management (GOAs distributed to Backend as well Operational Contracts
initialized in SRM and created directly in Backend) in via SRM?
Consignment Items usually do not create a committment till the material is taken.
Nevertheless these materials are a great source for savings as well natural source
of supply using them via GOAs / Contracts distributed / created via SRM.
Anybody came across that requirement and put a successfull solution in place?
I am looking forward to any of your insights and / or solutions to be discussed.
(I am not missing any config, OSS Notes, etc. I aware of existing documentation)
Many thanks,
Claudia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
<u>Please refer to this SAP OSS note, which will help.</u>
Note 646903 - Global outline agreement: Tips and tricks
<u>Other related useful links.</u>
http://help.sap.com/saphelp_srm50/helpdata/en/17/303f412124de2be10000000a1550b0/frameset.htm
http://help.sap.com/saphelp_srm50/helpdata/en/0e/c3ab3c5f8e1409e10000000a114084/frameset.htm
Regards
- Atul